Clean Water State Revolving Fund (CWSRF)
Change orders to construction contracts may be necessary from time to time during the period of project construction to increase or decrease the contract cost or work, revise the completion date, alter the design, or to implement any deviation from original contract terms and conditions. Loan recipients shall
promptly notify the Construction Grants
The recipient must obtain prior DENR-DWQ approval for any change orders in excess of $100,000 or any change orders which would necessitate an increase in the loan amount. The recipient should submit two (2) properly executed copies of change orders to the Construction Inspection Group. Change order forms should indicate the project number, the correct change order number, name of contractor, contract number, and the date the change order was signed by all parties. A copy of the Change Order Checklist should be completed and submitted with each change order. All items indicated on the checklist must be adequately addressed prior to approval. Once the Recipient signs a change order, he obligates himself to the Contractor. The State is not obligated to approve the change order or reimburse the Recipient. The CIG will perform preliminary eligibility reviews of unexecuted change orders upon request, however all supporting documentation must be included. |
![]() |
|
|
Home |
Personnel Directory |
How to Find Us |
Financial Assistance Programs Tax Certification | Permits & Engineering © 2000 - North Carolina Construction Grants and Loans Section North Carolina Department of Environment and Natural Resources |
|
![]() |