HOME

|
Permits and Engineering
Sanitary Sewer Evaluation Survey (SSES) Outline
-
Summary, Conclusion, and Recommendations
Summarize the problem
and discuss the basis for selecting the proposed rehabilitation area
(e.g. overflows/bypasses, 90% of design capacity, 80% of design
capacity, other). An SSES is considered an engineering report;
therefore, the front page or cover should be signed and sealed by an
engineer licensed to practice in North Carolina.
- History
Provide a short
discussion of any previous sewer system rehabilitation and its
geographic relationship to the currently proposed work. If applicable,
the report should include a brief history of overflows/bypasses and
their location, numbers of Notices of Violation, and/or other pertinent
information to support the need for the rehabilitation.
- Current
Situation
- Provide a
description of the collection system to include the following:
- The age of
system, general materials, total footage and inch miles of sewer lines
in the system and in the project area.
- The number of
pump stations, their age, capacities, and condition.
- Provide a copy
of any SOC or sewer moratorium that applies to the system.
- If applicable,
also provide copies of any associated inter-local agreements.
- Rehabilitation
- Provide a brief
description of the proposed rehabilitation including the methodology
proposed; whether the existing lines will be lined, replaced, sized
larger than the existing lines; and if the work will be done within
existing rights-of-way or easements.
- Provide the
approximate flow expected to be removed by the proposed work.
- Provide an
estimate of the total project costs including capital costs,
engineering fees, contingencies, and if applicable, the 2% State
Revolving Fund (SRF) closing cost.
- Provide a map of
the proposed repairs that identifies manholes, pump stations, pipe
sizes, and pipe lengths.
- Provide a plan for
monitoring the collection system after completion of the project to
evaluate its effectiveness.
- User Charges
and Eligibility
The report must
include the current and expected user charges for a typical residential
customer using 5,000 gallons per month. Expected user charges must be
sufficient to pay back the loan and should be based on the project's
first year billable flow.
Funding of service
lines is limited to the portion within the sewer easement or
rights-of-way. Cost estimates should be developed accordingly.
- Environmental
Assessment
A Finding of No
Significant Impact (FNSI) may have to be prepared for the proposed
project. Therefore, the report must include an environmental assessment
(EA) of the proposed work. This information will be the basis for
developing any required FNSI. The EA will also enable reviewers to
determine whether the project is above or below the minimum criteria
threshold.
Guidance for preparing
an Environmental Assessment can be found at the following web site:
http://www.nccgl.net/fap/eaguide.htm.
Any applicable items should be addressed in the EA.
Relocation of pipes or
an increase in pipe size may require a permit. A more detailed
environmental assessment will be required for these types of projects.
- Public Participation
For projects funded through the SRF
program, a public hearing with an advertisement in a newspaper having
community-wide circulation is required if, as a result of the SRF loan,
the current user charges increase by more than 10% (See Section V).
Any required public hearing must
identify the problem, discuss the proposed rehabilitation, identify the
size of the SRF loan, and identify the effect on a typical residential
user's monthly sewer bill.
After the hearing is conducted a
transcript or detailed summary of the hearing and an affidavit of
publication of the hearing notice must be provided.
Provide three (3) copies of the SSES
for our review.
Revised 11/24/03, 8/15/05
|
 |